WILSON
2000
TIMELINE
TO OCCUPANCY (DRAFT) |
|
MAY
1998
|
- Review
Charge
- Review
Parameters
- Review
Previous Wilson Study Committee Work
- Identify
Add’l Data Collection Areas
- Survey
Staff, Community, Parents, Students
- Conduct
Site Visits
- Collect
Data
- Sort
and Prioritize Data within Context of Previous
Work
- Report
to Board
|
| JUNE
1998 |
- Select
Architect
- Review
Capital Development Board Requirements
- Identify
District Requirements
- Prepare
Solicitation
- Seek
bids
- Interview
- Visit
completed projects
- Make
recommendation to Board
- Board
engage architect
|
| JULY
1998 |
- Develop
Concept
- Ascertain
Program Needs
- Ascertain
Instructional Requirements
- Ascertain
Available Space
- Ascertain
Adequacy of Possible School Sites
- Envision
Classroom of Future
- Identify
Instructional Areas
- Develop
Building Configuration
- Conceptualize
Space, Use, and Flow
|
| AUGUST
1998 |
- Develop
Concept
- Continue
July Work
- Develop
Preliminary Cost Estimates
- Ascertain
ranking and potential for funding
- Determine
whether to continue work
- Report
to Board with preliminary recommendations
|
| SEPTEMBER
1998 |
|
| OCTOBER
1998 |
- Develop
Specifications (con’t.)
|
| NOVEMBER
1998 |
- Develop
Specifications (con’t.)
- Develop
preliminary cost estimates
- Ascertain
State Construction Grant Entitlement Award
|
DECEMBER
1998 |
- Board
approve specifications
- Obtain
CDB approval and funding level
- Committee
develop financing
- Staff
Updated on Project
|
| JANUARY
1999 |
- Board
approve final budget and funding levels, financing
plan
- Architect
solicits bids
- Committee
develops transition plan
|
| FEBRUARY
1999 |
- Bids
received, reviewed, qualifications of contractors
ascertained
|
| MARCH
1999 |
- Bid
award made, contract entered into
|
| APRIL
1999 |
| |
| MAY
1999 Construction of Addition (con’t.)
|
JUNE
1999 Construction of Addition (con’t.)
|
JULY
1999 Construction of Addition (con’t.)
|
| AUGUST
1999 Construction of Addition (con’t.)
|
SEPTEMBER
1999 Construction of Addition (con’t.)
|
OCTOBER
1999 Construction of Addition (con’t.)
|
| NOVEMBER
1999 Construction of Addition (con’t.)
|
DECEMBER
1999 Construction of Addition (con’t.)
|
JANUARY
2000 Construction of Addition (con’t.)
|
| FEBRUARY
2000 Construction of Addition (con’t.)
|
MARCH
2000 Construction of Addition (con’t.)
|
APRIL
2000 Construction of Addition (con’t.)
|
| MAY
2000
Construction of Addition (con’t.)
|
JUNE
2000
Begin remodeling original building
|
JULY
2000
Move into new addition |
AUGUST
2000 Occupy new addition |
SEPTEMBER
2000 Remodel original building (con’t.)
|
OCTOBER
2000 Remodel original building (con’t.)
|
NOVEMBER
2000 Remodel original building (con’t.)
|
DECEMBER
2000 Remodel original building (con’t.)
|
JANUARY
2001 Remodel original building (con’t.)
|
FEBRUARY
2001 Remodel original building (con’t.) |
MARCH
2001 Remodel original building (con’t.)
|
APRIL
2001
Remodel original building (con’t.) |
MAY
2001 Remodel original building (con’t.)
|
JUNE
2001 Remodel original building (con’t.)
|
JULY
2001
Move into remodeled original building |
AUGUST
2001 Occupy remodeled original building
|
SEPTEMBER
2001 Dedicate buildings |
OCTOBER
2001 Evaluate Project |