TIMELINE TO OCCUPANCY (DRAFT)
MAY 1998
  • Convene Committee:
  • Review Charge
  • Review Parameters
  • Review Previous Wilson Study Committee Work
  • Identify Add’l Data Collection Areas
  • Survey Staff, Community, Parents, Students
  • Conduct Site Visits
  • Collect Data
  • Sort and Prioritize Data within Context of Previous Work
  • Report to Board
JUNE 1998
  • Select Architect
  • Review Capital Development Board Requirements
  • Identify District Requirements
  • Prepare Solicitation
  • Seek bids
  • Interview
  • Visit completed projects
  • Make recommendation to Board 
  • Board engage architect
JULY 1998
  • Develop Concept
  • Ascertain Program Needs
  • Ascertain Instructional Requirements
  • Ascertain Available Space
  • Ascertain Adequacy of Possible School Sites
  • Envision Classroom of Future
  • Identify Instructional Areas
  • Develop Building Configuration
  • Conceptualize Space, Use, and Flow
AUGUST 1998
  • Develop Concept
  • Continue July Work
  • Develop Preliminary Cost Estimates
  • Ascertain ranking and potential for funding
  • Determine whether to continue work
  • Report to Board with preliminary recommendations
SEPTEMBER 1998
  • Develop Specifications
OCTOBER 1998
  • Develop Specifications (con’t.)
NOVEMBER 1998
  • Develop Specifications (con’t.)
  • Develop preliminary cost estimates
  • Ascertain State Construction Grant Entitlement Award

DECEMBER 1998

  • Board approve specifications
  • Obtain CDB approval and funding level
  • Committee develop financing 
  • Staff Updated on Project
JANUARY 1999
  • Board approve final budget and funding levels, financing plan
  • Architect solicits bids
  • Committee develops transition plan
FEBRUARY 1999
  • Bids received, reviewed, qualifications of contractors ascertained
MARCH 1999
  • Bid award made, contract entered into
APRIL 1999
  • Construction Begins
 

 
 
MAY 1999 Construction of Addition (con’t.)
JUNE 1999 Construction of Addition (con’t.)
JULY 1999 Construction of Addition (con’t.)
AUGUST 1999 Construction of Addition (con’t.)
SEPTEMBER 1999 Construction of Addition (con’t.)
OCTOBER 1999 Construction of Addition (con’t.)
NOVEMBER 1999 Construction of Addition (con’t.)
DECEMBER 1999 Construction of Addition (con’t.)
JANUARY 2000 Construction of Addition (con’t.)
FEBRUARY 2000 Construction of Addition (con’t.)
MARCH 2000 Construction of Addition (con’t.)
APRIL 2000 Construction of Addition (con’t.)
MAY 2000
Construction of Addition (con’t.)
JUNE 2000
Begin remodeling original building
JULY 2000
Move into new addition
AUGUST 2000 Occupy new addition
SEPTEMBER 2000 Remodel original building (con’t.)
OCTOBER 2000 Remodel original building (con’t.)
NOVEMBER 2000 Remodel original building (con’t.)
DECEMBER 2000 Remodel original building (con’t.)
JANUARY 2001 Remodel original building (con’t.)
FEBRUARY 2001 Remodel original building (con’t.)
MARCH 2001 Remodel original building (con’t.)
APRIL 2001
Remodel original building (con’t.)
MAY 2001  Remodel original building (con’t.)
JUNE 2001 Remodel original building (con’t.)
JULY 2001
Move into remodeled original building
AUGUST 2001 Occupy remodeled original building
SEPTEMBER 2001 Dedicate buildings
OCTOBER 2001 Evaluate Project
 



Pekin Public Schools District 108
501 Washington Street
Pekin, IL 61554
Phone: 309.477.4740
Fax: 309.477.4701

This page was last updated on Wednesday, July 21, 2004
© 1996-2004 Pekin Public Schools District 108. All Rights Reserved.
Legal Disclamer | Feedback Form | Sitemap | Interactive Map | Help