ADDENDUM 3
WILSON 2000 PROJECT
Issued 10-02-98
The following questions requesting clarification have been received to date. The answer to the question has been italicized to distinguish it from the question. This Addendum 2 should be added to and incorporated in the Request for Statement of Interest and Qualifications issued September 1998.
General Instructions, item #7, page 3. We were in attendance at the mandatory conference, but would not be the lead architect as we are an engineering firm. Our Consortium partner (the architect), also in attendance, has chosen not to respond. Could we engage a new architect partner and, vis-a-vie our attendance, still respond?
Yes. So long as one member of a consortium was present at the mandatory meeting the requirement of Item #7 of the General Instructions—especially when read within the context of the first sentence of the Scope of the Project—would be satisfied.
General Instructions, item #4, page 3. How many copies of the response do you require?
We require one original set of forms and your attachments completed and signed in blue ink and four copies thereof for our team of readers.