Action Plan

GOAL: Complete the Wilson and Washington construction projects and prepare for the remodeling of "old" Wilson and the 1961 addition of Washington.

 

RELATIONSHIP TO DISTRICT/ SCHOOL GOAL: Complete the Wilson and Washington construction projects and prepare for the remodeling of "old" Wilson and the 1961 addition of Washington.

 

WHAT?

What actions need to be taken to complete the task?

RESULTS?

What data or documents will indicate closure or success for each action?

TIMEFRAME?

When will each action be conducted?

WHO?

Who needs to be involved with each action?

RESOURCES?

What tools/strategies need to be collected, developed or organized to complete the task?

Attend monthly construction meetings.

 

 

 

 

Meeting notes.

Change orders.

PSA communications.

Schedules.

Monthly

Building principal

Facilities Manager

PSA

PJ Hoerr

Progress reports.

Architects recommendations.

Contractors updates.

Schedules

Change Orders

 

Attend monthly pay out meetings.

 

 

 

Meeting notes.

Change orders.

Pay Requests.

Schedules

First Wednesday of each month at 1:30

Building principal

Facilities Manager

Superintendent

Business Manager

PSA

PJ Hoerr

Pay requests

Schedule updates

Change orders.

Monitor change orders.

 

 

 

 

 

PSA documentation.

Change order requests.

Estimates.

Priority Needs.

Contingency Budget.

On-going

Facilities Manager

Superintendent

Business Manager

PSA personnel

PJ Hoerr personnel

Contingency Budget monitoring.

Change orders

PSA communications.

Finalize student furniture order.

Budget.

Specifications.

Bids

Delivery/ Set up

Specifications in spring, 2000

Bids in summer, 2000

Washington scheduled for delivery fall, 2000

Wilson scheduled for delivery spring, 2001

Building principals

Teacher Committee

Business Manager

PSA personnel

Vendors

Budget

Specifications

Bids

Implementation Plans

Finalize teacher furniture order.

Budget

Specifications.

Bids

Delivery/ Set up

Specifications in January, 2001

Bids in March, 2001

Washington and Wilson scheduled for delivery summer, 2001

 

Building principals

Teacher Committee

Business Manager

Vendors

Budget

Specifications

Bids

Implementation plan.

Work with facilities committee to address future construction needs for Washington 61 and old Wilson.

Needs Assessment

Prioritization.

Recommendations for board for summer, 2001

Long range plan outlined for future work.

Needs identified by December, 2000

Recommendations by February, 2001

Plan by spring, 2001

Facilities Committee

Board of Education

Needs Assessment

Budget

 

 

Prepare to occupy Washington 29./ Plan rededication ceremony.

Moving plan.

Rededication ceremony plan.

 

Occupancy in November, 2000

Ceremony in February, 2001

Facilities Manager

Building Principal

Implementation Plans

Ceremony Plans

Prepare to occupy new Wilson. Plan dedication ceremony.

Moving plan.

Team Assignments

Dedication ceremony

Occupancy by Report Card Day, spring 2001

Team Assignments by April, 2001

Dedication Ceremony May, 2001

Facilities Manager

Building Principal

 

 

 

 

 

 

Implementation Plans

Assignment Input

Ceremony Plans