- Held monthly construction
meetings to monitor progress of construction projects.
- Held monthly pay
out meetings to authorize pay requests of architect and contractor.
- Prepared specifications
for student and teacher furniture. Received bids and awarded contracts
for student and teacher furniture.
- Held dedication
ceremony for Washington School on February 3, 2001.
- Resolved conflict
between architect, contractor and district over interpretation of tuck
pointing of Washington School and terrazo cleaning at Washington School.
- Resolved property
issues with property owners west of Wilson School. Received signed license
agreements for all owners to protect district property for the future.
- Moved students
and staff into newly renovated Washington School.
- Moved students
and staff into new Wilson School.
- Identified priorities
for renovation of "old" Wilson and the 1961 addition of Washington
School.
- Prepared specifications,
received bids and awarded contract for window replacement at "old"
Wilson for the summer of 2001.
- Received 45 % of
state construction grant when 50 % completion ($4,411,167.75).
|
- Preparing for dedication
of Wilson School on August 26, 2001.
- Finalizing punch
list items for Washington School.
- Finalizing punch
lists items for Wilson School.
- Replacing windows
at "old" Wilson.
- Renovating five
classrooms at "old" Wilson for preschool programs for the
2001-2002 school year.
- Renovating learning
center at Washington School for the 2001-2002 school year.
- Painting 1961 Washington
classrooms, halls and cafeteria.
- Refurbishing existing
street lockers in 1961 halls.
- Receiving final
%10 of construction grant ($980,259.25) . Substantial letter of completion
was received on June 1, 2001.
|
- Will implement
three-year Phase In plan for "old" Wilson.
- Will implement
the facilities committee plan for the renovation of the 1961 addition
of Washington School.
|